Table 5 Cost of deploying targets

From: Delivering ‘tiny targets’ in a remote region of southern Chad: a cost analysis of tsetse control in the Mandoul sleeping sickness focus

Item (percentage of two years’ total costs)

2015

(USD)

2016

(USD)

Specialised equipment (25.8%)

   Targetsa

3000

3000

   Target insurance and freight

1050

930

   Target assembly and fixing: cutting up 12,000 sticks and assembling of targets

506

101

   String, wire and glue

452

295

Transport (14.4%)

   Vehicle hire

1973

2108

   Fuel

422

547

   Canoe hire (5 days, from several jetties)

84

84

Staff (43.0%)

   Share of staff salaries

3188

3895

   Travel allowances

3744

4755

Local labour (3.8%)

   Supervisor, guard

110

599

   CSSEs incentive payments

658

Administrative support (9.1%)

1599

1698

Consumables and equipment (3.9%)

   GPS sets (depreciation)

68

68

   GPS sets batteries

101

51

   Fuel for generator

49

74

   Digital camera (depreciation)

105

105

   Stationery (markers, batteries, etc.)

68

9

   Machetes (depreciation, 2 year life)

253

253

   Sundries, including internet

84

134

Total

16,856

19,364

Cost per km2 protected

20.1

23.1